Skip to main content
All Stories
For Predictability6 min read

The Predictability Problem

How a 12-person team went from 58% sprint completion to 89%—by measuring what Jira couldn't see

Sprint Completion
58%89%
+31 points
Cycle Time (P50)
5.2 days1.9 days
63% faster
WIP per Developer
4.7 PRs2.1 PRs
55% reduction
Flow Efficiency
31%68%
+37 points

Executive Summary

A 12-engineer team at CloudSync Solutions consistently delivered only 58% of sprint commitments despite working extended hours. Analysis of 847 pull requests over 90 days revealed the root cause wasn't estimation accuracy—it was work-in-progress overload creating invisible queues. After implementing WIP limits and flow-based practices, sprint completion rose to 89% within 8 weeks.

The Initial Hypothesis

CloudSync's engineering manager, James Okonkwo, had a theory: the team was bad at estimation. Stories consistently took 2-3x longer than planned. The obvious solution seemed to be estimation training and story point recalibration.

The data told a different story entirely.

Key Finding: The WIP Problem

Analysis of GitHub data revealed a critical pattern:

Average Work-in-Progress: 4.7 open PRs per developer

Each engineer was simultaneously juggling nearly 5 pieces of work. The cognitive load was unsustainable, and the queuing effects were devastating.

Cycle Time Distribution

PercentileObservedDORA EliteGap
P50 (Median)5.2 days1.5 days+247%
P758.1 days3.0 days+170%
P9512.8 days7.0 days+83%

The high variance (P95 nearly 2.5x P50) made sprint planning essentially guesswork. No amount of estimation training would fix this—the problem was throughput, not sizing.

Root Cause: Little's Law in Action

The data confirmed what queuing theory predicts: high WIP causes exponential delay growth. With 4.7 concurrent items per developer and reviews averaging 18 hours wait time, work spent 42% of its lifecycle waiting—not being worked on.

Results After Intervention

WeekCycle Time (P50)WIP/DevSprint Completion
0 (baseline)5.2 days4.758%
24.1 days3.267%
42.8 days2.478%
81.9 days2.189%

Three months post-intervention, sprint completion stabilized at 87-92% with no increase in working hours.

The Lesson

"Sprint predictability isn't about better estimation—it's about reducing the invisible queues where work gets stuck."

About CloudSync Solutions

A B2B data integration platform serving mid-market enterprises across finance, healthcare, and retail. Founded in 2020, they've grown to 45 employees with 12 engineers.

Names and some details have been changed to protect confidentiality. Metrics are representative of actual improvements.

What's hiding in your GitHub data?

Every engineering organization has invisible bottlenecks, hidden risks, and unrecognized performers. Find yours in minutes.

Prefer a walkthrough? Talk to sales